Building Information

PreK-8-StartingFoundation

 New PreK-8 Building Update

Workers are still making progress on the new PreK-8 building.
 
Manlin White (Plumbing) is working on underground area A (west wing) and layout for digging in areas B & C (Administration areas and shower rooms)
 
Lake Erie Electrical is working with the city along the north access road to bring in the primary and communications conduit.
 
Studer Obringer (general trades) has informed us that ALL footers will be complete by the end of the week (weather permitting).  They have started laying foundation block, water proofing the foundation, and installing foundation tile.
 
RFC (Site Prep) has run water lines into the building and are working on compacting trenches from utilities (sewer, water line, storm line). 
 

 

 

 "Live Snapshot"  on hold...

 

 Unfortunately due to server weather conditions the New Building camera is unavailable. We are in the process of ordering a new one and will have it back up and running soon.

 

 

Thank you for your patience!

 

                                    